THE PIONEER PROJECT
– EXTENSION IN RECORD TIME

LEVERKUSEN II
Extended during ongoing operation | Approx. 2,200 m² GFA | 2 MW IT power load

After just over one year of operation, the pioneer data centre in North Rhine-Westphalia was extended. The data centre now boasts approx. 2,200 m² and an IT power load of up to 2 MW. CDC awarded the contract to a general contractor. This is the first data centre built using modular techniques that has been extended during ongoing operation. An industry sensation.